How does work flow from one state to the next in a team Kanban board?

  1. Team members push work to the next state whenever possible

  2. Work flows automatically depending on the due date

  3. Team members pull work from the previous state without impacting current state WIP constraints

  4. Work is moved based on priority set by the Product Owner

The correct answer is: Team members pull work from the previous state without impacting current state WIP constraints

In a team Kanban board, work flows through different states based on a pull system. This means that team members actively pull work items from the previous state into the next, rather than pushing them forward. This approach allows teams to maintain control over their workflow and ensures they only take on work that they can handle without exceeding their current work-in-progress (WIP) limits. By pulling work, teams can prioritize tasks more effectively and respond to changing circumstances without overcommitting. This practice helps to optimize flow and enhances overall efficiency within the team. When using WIP constraints, team members are encouraged to consider their available capacity before taking on new work, which is a key principle of Kanban. This self-regulation allows teams to maintain a sustainable pace and continuously improve their processes. Thus, the correct understanding of how work flows in a team Kanban board aligns with the principles of agility and efficiency inherent in Kanban methodologies.