If a team achieved less than 80% predictability during the Inspect and Adapt event, which action should the Scrum Master avoid?

  1. Facilitating a discussion on improvements

  2. Deciding improvement actions for the team to implement

  3. Encouraging team feedback on their processes

  4. Gathering metrics for future planning

The correct answer is: Deciding improvement actions for the team to implement

In a situation where a team has achieved less than 80% predictability during the Inspect and Adapt event, it is crucial for the Scrum Master to foster a culture of self-organization and empowerment within the team. By deciding on improvement actions for the team to implement, the Scrum Master undermines the autonomy of the team and misses an essential aspect of Agile principles, which emphasize that teams should take ownership of their own processes and solutions. Empowering the team to brainstorm and discuss potential improvements allows for a greater sense of accountability and buy-in, which can lead to more effective and sustainable changes. The Inspect and Adapt event is an opportunity for the team to reflect on their performance collaboratively, assess their processes, and determine what changes they believe are necessary to enhance predictability and overall effectiveness. Facilitating discussions, encouraging feedback, and gathering metrics all serve to enhance the team's understanding of their processes, promote open communication, and empower the team to take charge of their own improvements. By avoiding a directive approach and instead supporting a collaborative environment, the Scrum Master can guide the team towards more meaningful and effective improvements.