Who should participate in the Inspect and Adapt event?

  1. The project manager only

  2. The entire Agile Release Train

  3. Only the Scrum Masters

  4. External stakeholders

The correct answer is: The entire Agile Release Train

The entire Agile Release Train participating in the Inspect and Adapt event is crucial for fostering collaboration and continuous improvement across multiple teams within the train. This event serves as a key opportunity for team members, including Scrum Masters, Product Owners, developers, and business stakeholders, to reflect on the previous Program Increment and make adjustments to improve their processes and delivery. By involving the entire Agile Release Train, the collective insights and experiences of all participants can be leveraged to identify areas for enhancement, address impediments, and reinforce alignment on goals. This collaborative effort helps to ensure that everyone has a shared understanding of what did and didn't work during the increment and promotes a culture of transparency and shared ownership in the team’s success. Engaging only a select few individuals—like just the project manager or only the Scrum Masters—would limit the perspectives and ideas shared, which is counterproductive to the essence of Agile principles that emphasize teamwork and collective responsibility. Therefore, the inclusion of the entire Agile Release Train is essential to drive meaningful change and sustain a learning culture within the organization.